Key Points
- 01Korea names preferred bidders for 1,194 MW of ESS capacity
- 02Third ESS central contract round tops first two rounds combined
- 03Tender covered 14 sites after initially offering 1,180 MW
- 04Final awarded volume due December 4, buildout by February 2029
Record ESS tender awards 1,194 MW of capacity
South Korea has selected preferred bidders for 1,194 megawatts of energy storage system capacity in its largest ESS auction to date. The third ESS central contract market round covers 14 project sites and surpasses the combined 1,128 MW awarded in the first and second rounds. The projects are aimed at expanding large battery facilities that store electricity and release it when needed to support the power system.
The Ministry of Climate, Energy and Environment and the Korea Power Exchange announced the preferred bidders on November 26. Final awarded volumes will be confirmed on December 4 after consultations with the bidders, within rules that allow contracted capacity of up to 105% of the tendered amount.
Geographic spread and project scale
The 14 sites include six in South Jeolla province, five in North Jeolla province, one in South Chungcheong province and two on Jeju Island. By capacity, South Jeolla (Jeonnam) accounts for 539 MW and North Jeolla (Jeonbuk) 480 MW. The Nonsan site in South Chungcheong holds 96 MW, while two sites in Pyoseon on Jeju Island total 79 MW.
The tender initially sought 1,180 MW, including 1,100 MW on the mainland and 80 MW on Jeju Island, equivalent to about 7.08 gigawatt-hours of battery storage. The 1,194 MW covered by preferred bids is 14 MW higher than the originally offered volume, in line with guidelines permitting awards above the initial capacity.
Bidding dynamics and participation
About 60 companies are reported to have taken part in the third ESS central contract market tender. The selected project companies and the battery suppliers for the installations have not been disclosed. The round drew attention in part because LG Energy Solution chose not to participate, stating it would focus on supplying volumes it had already secured.
Authorities broadened the pool of candidate sites compared with previous rounds and assessed the need to connect ESS facilities in each region based on nationwide grid conditions. Evaluation criteria continued to include fire safety and contributions to industrial competitiveness, alongside the potential of projects to stabilize the grid.
Implementation timeline and next steps
Developers selected as preferred bidders must obtain power generation business permits by August next year. Construction of the ESS facilities is required to be completed by February 2029. These timelines apply across all 14 project locations and define the buildout schedule for the awarded capacity.
The government has used three rounds of the ESS central contract market to advance energy storage introduction targets set in the basic power supply and demand plan. With the third round now identifying preferred bidders, a fourth auction is scheduled for the first half of next year to continue expanding the country’s ESS capacity.
Key Takeaways
- 01South Korea’s third ESS auction marks a major step-up in storage deployment, awarding preferred bidder status for more capacity than the first two rounds combined.
- 02The 1,194 MW of selected projects slightly exceeds the initial 1,180 MW on offer, reflecting auction rules that allow awarding up to 105% of tendered capacity.
- 03Regional allocations heavily favor South and North Jeolla provinces, while also adding capacity in South Chungcheong and Jeju to diversify grid support.
- 04Project developers face a defined execution window, with permits due by August next year and completion required by February 2029, anchoring the rollout schedule.
- 05A planned fourth ESS central contract market in the first half of next year signals continued policy support for scaling battery storage within Korea’s power system.