AAPL+0.69%MSFT+0.96%GOOGL+1.78%NVDA+3.63%AMZN+1.69%SPCX+1.42%TSM+2.92%AVGO+2.47%META+1.21%TSLA+1.46%LLY+0.01%WMT+0.08%JPM-0.04%BRK-B+0.02%V+0.01%SKHY0.00%AMD+3.30%MU+2.48%XOM0.00%JNJ+0.15%MA+0.07%ABBV+0.08%ASMLa-9.33%COST+0.19%1398.HK+0.25%KO+0.03%CVX+0.03%0700.HK-1.26%PG+0.09%CSCO+0.07%0939.HK0.00%1816.HK+3.45%HD+0.06%3988.HK-1.13%BAC+0.05%GE0.00%0857.HK-0.49%ORCL-0.01%UNH+0.02%1288.HK-0.45%PM+0.02%0005.HK-3.08%NVS-0.01%HSBA.L-3.62%INTC+3.30%AZN-0.01%MS+0.02%RTX+0.14%ORp-0.36%TMO+0.14%GBPTRY+0.41%GBPHKD+0.32%GBPMXN-0.28%USDILS+0.16%USDCOP-0.04%GBPSGD0.00%PLNJPY0.00%GBPZAR0.00%USDZAR0.00%USDPLN0.00%EURNZD0.00%AUDCHF0.00%EURSEK0.00%GBPUSD0.00%GBPCHF0.00%USDDKK0.00%USDHKD0.00%CADJPY0.00%GBPCAD0.00%NZDCAD0.00%GBPNZD0.00%GBPAUD0.00%EURCAD0.00%EURJPY0.00%EURNOK0.00%EURUSD0.00%CADCHF0.00%NZDCHF0.00%NZDSGD0.00%EURCZK0.00%NOKJPY0.00%AUDCAD0.00%CHFSGD0.00%SGDJPY0.00%AUDSGD0.00%NZDUSD0.00%GBPJPY0.00%EURGBP0.00%AUDNZD0.00%AUDJPY0.00%AUDUSD0.00%USDJPY0.00%USDCNH0.00%EURCHF0.00%USDMXN0.00%USDNOK0.00%USDTHB0.00%USDTRY0.00%USDSEK0.00%USDCAD0.00%USDCHF0.00%EURHKD0.00%EURAUD0.00%AUDNOK0.00%EURCNH0.00%EURZAR0.00%EURSGD0.00%AUDDKK0.00%CHFSEK0.00%USDSGD0.00%CHFJPY0.00%NZDJPY0.00%CHFNOK0.00%EURDKK0.00%EURPLN0.00%NZDMXN0.00%GAGUSD0.00%W10.00%XAGUSD0.00%HG10.00%S10.00%C10.00%XNGUSD0.00%USOIL0.00%XAUUSD0.00%SUGAR0.00%COTTON0.00%COFFEE0.00%BTCUSD+2.62%ETHUSD+77.41%USDTUSD+0.09%XRPUSD+64.83%SOLUSD+72.04%TRXUSDT+1.22%ZECUSDT+4.60%XMRUSDT+7.10%DOGEUSD+72.43%LINKUSD+1.09%XLMUSD+1.84%BCHUSDT+2.47%LTCUSD+64.72%UNIUSD+5.11%TONUSD+74.91%SUIUSD-0.60%HBARUSDT+0.43%TAOUSDT+2.40%AAVEUSD-0.66%ONDOUSDT-0.59%DOTUSDT-1.60%ICPUSDT-5.65%WLDUSDT-0.52%ARBUSDT-0.81%ATOMUSDT-3.84%INJUSDT-4.42%STXUSDT+2.91%PYTHUSDT+0.40%TIAUSDT-1.31%FETUSDT-3.16%SEIUSDT-1.94%JUPUSDT-4.27%GRTUSDT+0.60%OPUSDT+0.63%IOTAUSDT-1.74%POLUSDT-0.11%WIFUSDT-2.78%AXSUSDT+0.59%EOSUSDT+0.77%IMXUSDT-3.33%FARTCOINUSDT-0.08%GALAUSDT-2.18%DYDXUSDT-3.45%ORDIUSDT-0.23%NOTUSDT-1.52%RONINUSDT+0.62%AAPL+0.69%MSFT+0.96%GOOGL+1.78%NVDA+3.63%AMZN+1.69%SPCX+1.42%TSM+2.92%AVGO+2.47%META+1.21%TSLA+1.46%LLY+0.01%WMT+0.08%JPM-0.04%BRK-B+0.02%V+0.01%SKHY0.00%AMD+3.30%MU+2.48%XOM0.00%JNJ+0.15%MA+0.07%ABBV+0.08%ASMLa-9.33%COST+0.19%1398.HK+0.25%KO+0.03%CVX+0.03%0700.HK-1.26%PG+0.09%CSCO+0.07%0939.HK0.00%1816.HK+3.45%HD+0.06%3988.HK-1.13%BAC+0.05%GE0.00%0857.HK-0.49%ORCL-0.01%UNH+0.02%1288.HK-0.45%PM+0.02%0005.HK-3.08%NVS-0.01%HSBA.L-3.62%INTC+3.30%AZN-0.01%MS+0.02%RTX+0.14%ORp-0.36%TMO+0.14%GBPTRY+0.41%GBPHKD+0.32%GBPMXN-0.28%USDILS+0.16%USDCOP-0.04%GBPSGD0.00%PLNJPY0.00%GBPZAR0.00%USDZAR0.00%USDPLN0.00%EURNZD0.00%AUDCHF0.00%EURSEK0.00%GBPUSD0.00%GBPCHF0.00%USDDKK0.00%USDHKD0.00%CADJPY0.00%GBPCAD0.00%NZDCAD0.00%GBPNZD0.00%GBPAUD0.00%EURCAD0.00%EURJPY0.00%EURNOK0.00%EURUSD0.00%CADCHF0.00%NZDCHF0.00%NZDSGD0.00%EURCZK0.00%NOKJPY0.00%AUDCAD0.00%CHFSGD0.00%SGDJPY0.00%AUDSGD0.00%NZDUSD0.00%GBPJPY0.00%EURGBP0.00%AUDNZD0.00%AUDJPY0.00%AUDUSD0.00%USDJPY0.00%USDCNH0.00%EURCHF0.00%USDMXN0.00%USDNOK0.00%USDTHB0.00%USDTRY0.00%USDSEK0.00%USDCAD0.00%USDCHF0.00%EURHKD0.00%EURAUD0.00%AUDNOK0.00%EURCNH0.00%EURZAR0.00%EURSGD0.00%AUDDKK0.00%CHFSEK0.00%USDSGD0.00%CHFJPY0.00%NZDJPY0.00%CHFNOK0.00%EURDKK0.00%EURPLN0.00%NZDMXN0.00%GAGUSD0.00%W10.00%XAGUSD0.00%HG10.00%S10.00%C10.00%XNGUSD0.00%USOIL0.00%XAUUSD0.00%SUGAR0.00%COTTON0.00%COFFEE0.00%BTCUSD+2.62%ETHUSD+77.41%USDTUSD+0.09%XRPUSD+64.83%SOLUSD+72.04%TRXUSDT+1.22%ZECUSDT+4.60%XMRUSDT+7.10%DOGEUSD+72.43%LINKUSD+1.09%XLMUSD+1.84%BCHUSDT+2.47%LTCUSD+64.72%UNIUSD+5.11%TONUSD+74.91%SUIUSD-0.60%HBARUSDT+0.43%TAOUSDT+2.40%AAVEUSD-0.66%ONDOUSDT-0.59%DOTUSDT-1.60%ICPUSDT-5.65%WLDUSDT-0.52%ARBUSDT-0.81%ATOMUSDT-3.84%INJUSDT-4.42%STXUSDT+2.91%PYTHUSDT+0.40%TIAUSDT-1.31%FETUSDT-3.16%SEIUSDT-1.94%JUPUSDT-4.27%GRTUSDT+0.60%OPUSDT+0.63%IOTAUSDT-1.74%POLUSDT-0.11%WIFUSDT-2.78%AXSUSDT+0.59%EOSUSDT+0.77%IMXUSDT-3.33%FARTCOINUSDT-0.08%GALAUSDT-2.18%DYDXUSDT-3.45%ORDIUSDT-0.23%NOTUSDT-1.52%RONINUSDT+0.62%

Poland advances $52bn U.S.-backed nuclear project

NEWS

November 21, 2026 at 10:01 UTC

4 min read
Large nuclear reactor component in Polish yard symbolising U.S.-backed nuclear project with Westinghouse and Bechtel

Key Points

  • 01Poland plans a roughly $50–52bn nuclear plant with Westinghouse and Bechtel
  • 02Main EPC contract is now expected to be signed in 2027
  • 03Letter of intent launched early orders for long‑lead reactor components
  • 04Three AP1000 reactors aim to start up from 2036 to 2038, supplying about 10% of Poland’s power

Poland edges toward $50–52bn nuclear construction deal

Poland is nearing a major construction agreement with a U.S. consortium of Westinghouse Electric and Bechtel for its first nuclear power plant, a project valued at about $50–52 billion. State-owned Polskie Elektrownie Jądrowe (PEJ) expects to sign the main engineering, procurement and construction contract in 2027, after indicating that the end of the first quarter of that year is the most likely deadline. The plant will be built at the Lubiatowo-Kopalino site on the Baltic coast in Pomerania and is designed to host three Westinghouse AP1000 reactors.

PEJ and the consortium have already agreed on the contract’s principal commercial and legal terms, with both sides targeting substantial progress on remaining provisions and annexes before the end of 2026. The contract must still receive approvals from supervisory bodies and shareholders on both sides, a step PEJ’s management regards as as important as the negotiations themselves.

Project scale, technology and power targets

The planned three-reactor facility will use Westinghouse’s AP1000 technology and is expected to have a combined generating capacity of about 3,750 megawatts. Under current forecasts, the plant is projected to supply about 10% of Poland’s electricity once fully operational. Commercial operation of the first reactor is targeted for 2036, followed by the second in 2037 and the third in 2038.

PEJ plans to purchase nuclear fuel from several suppliers and store it on site to avoid dependence on a single source. The European Commission has estimated total investment in the AP1000 project at about $52 billion, reflecting both the reactors and associated infrastructure at the site.

Early procurement to protect 2028 construction start

To secure critical manufacturing capacity while negotiations continue, PEJ signed a letter of intent on November 19 with Westinghouse and Bechtel to broaden procurement of long-lead components, including reactor containment structures. The developer states that ordering such components early is intended to reduce the risk of construction delays and to help safeguard a planned 2028 start for nuclear construction. The November agreement builds on an earlier Engineering Development Agreement that already allowed design, licensing preparations and selected procurement to proceed before the EPC contract is signed.

In October, PEJ and Westinghouse agreed initial orders for large prefabricated steel-and-reinforced-concrete assemblies that will form parts of the AP1000 reactor buildings. Four Polish manufacturers—Energomontaz-Polnoc Gdynia, FAMAK, Mostostal Krakow and Mostostal Kielce—received conditional orders, subject to meeting the American Society of Mechanical Engineers’ NQA-1 nuclear quality-assurance standard. Additional major reactor-building structures are planned for manufacture in Japan and the United States, including a large auxiliary-building module.

Regulatory process and site preparation

PEJ submitted its nuclear construction-license application on March 31, and Poland’s National Atomic Energy Agency has up to 24 months to review it, excluding any time needed for supplemental documentation. A separate building permit is expected to be sought in 2027. Site preparation at the 740-acre Lubiatowo-Kopalino location is under way, including grading, drainage work and temporary access roads to ready the area for future nuclear construction, subject to regulatory approvals.

Gdansk University of Technology in northern Poland is partnering with Bechtel and the University of South Carolina to develop engineering expertise and workforce capabilities for nuclear energy projects, including this plant. Separately, Bechtel has signed a memorandum of cooperation with these universities to support recruitment and training of Polish engineering personnel as the project moves toward major construction activities.

Energy security and diversification goals

The nuclear program forms part of Poland’s broader strategy to strengthen energy security after historically relying on Russia for much of its energy. Following Russia’s 2022 invasion of Ukraine, Poland moved to end that dependence by increasing imports of U.S. liquefied natural gas and adopting U.S. nuclear technologies, while gradually phasing out coal in favor of renewable energy sources and natural gas. Polish Energy Minister Miłosz Motyka has stated that Russia used energy resources as a weapon and that Poland does not plan to resume doing business with Moscow.

In addition to the first plant at Lubiatowo-Kopalino, PEJ is in talks with French, Canadian and U.S. suppliers on the construction of a second nuclear power plant in another part of the country. Together, these projects are intended to support Poland’s long-term transition away from coal and reinforce its diversification of energy supply.

Key Takeaways

  • 01Poland’s first nuclear plant has progressed from concept to active contracting and early procurement, with a clear though extended timetable centered on a 2027 EPC signing.
  • 02By locking in long-lead component capacity and advancing site and licensing work, PEJ is trying to keep a 2028 construction start and mid‑2030s reactor start-up on track.
  • 03The project is both an energy transition and geopolitical initiative, aimed at replacing coal and reducing reliance on Russian energy through large-scale U.S.-backed nuclear generation.