Key Points
- 01HSBC sold about US$300 million of Project Jupiter loan exposure at a steep discount
- 02The loan relates to an US$18 billion financing for Oracle-linked Project Jupiter in New Mexico
- 03The sale followed Oracle’s force majeure notice and ongoing permitting and regulatory delays
- 04Project Jupiter is a key 2.45‑GW element of the Stargate AI infrastructure build-out
HSBC offloads $300m Project Jupiter loan stake
HSBC Holdings has offloaded a roughly US$300 million portion of a construction loan tied to Project Jupiter, a large data centre project in New Mexico linked to Oracle. The loan slice is part of an approximately US$18 billion financing package for the campus in Doña Ana County. The bank sold the exposure at a steep discount, with pricing reported in the mid‑80s cents on the dollar, implying it received around US$45 million less than par value.
The transaction involved a loan supporting a 2.45‑gigawatt facility that forms a major component of the Stargate AI infrastructure build‑out. The sale underscores lender caution around this particular project and its risks, rather than a routine portfolio adjustment.
Project setbacks and force majeure notice
Project Jupiter has faced significant local opposition and regulatory headwinds, including delays in obtaining critical air and pipeline permits. These issues have contributed to concerns about the project’s development trajectory. Despite its high‑profile role in the broader AI infrastructure plan, the New Mexico campus is described as troubled, with doubts over the future pace of the associated Stargate AI build‑out.
Oracle issued a force majeure notice to the project’s developer, a unit of Blue Owl Capital, in September. The notice allows Oracle to defer payments if the facility fails to meet its 2028 target date to come online. Oracle is reportedly not seeking to exit as the main tenant, and the company has stated that Project Jupiter remains on its planned schedule.
Wider implications for AI-linked debt
HSBC’s decision to sell at prices in the mid‑80s highlights how financing conditions for large AI infrastructure projects have become more cautious. Financial institutions are actively reassessing their exposure to AI‑related debt as they weigh project‑specific risks such as permitting delays and contractual uncertainty.
Market anxiety around AI financing has also been influenced by renewed regulatory pushback following a Democratic sweep in US elections and uncertainty over the pace of AI expansion after Jensen Huang’s abrupt departure from Nvidia. In this context, the discounted sale of the Project Jupiter loan stake illustrates how lenders are responding to a combination of regulatory, operational and sector‑level pressures.
Key Takeaways
- 01HSBC crystallized a sizable discount to exit its roughly US$300 million exposure to the Project Jupiter construction loan.
- 02Persistent permitting delays and regulatory pushback have turned a flagship AI data centre into a higher‑risk credit for lenders.
- 03Oracle’s force majeure notice provides payment flexibility while preserving its role as main tenant and stated commitment to the project timeline.
- 04The deal reflects a broader reassessment of AI‑linked infrastructure debt as political and market uncertainties cloud growth expectations.
References
- https://finance.yahoo.com/markets/stocks/articles/market-chatter-hsbc-sells-300-091146582.html?.tsrc=rss
- https://www.straitstimes.com/business/banking/hsbc-offloads-us300m-in-troubled-data-centre-loan-at-steep-discount
- https://ca.investing.com/news/stock-market-news/hsbc-offloads-300-million-troubled-ai-data-center-loan-at-steep-discount--report-4962296
- https://fourweekmba.com/ai-hsbc-sold-300m-oracle-tied-loan-in-mid-80s-45m-below-par/